Seoul ,Korea Data Center
A strong network to boost your business development

The LG U+ Gasan Data Center
The LG U+ Gasan data center is an international standard T3 data center in Gasan, Seoul, Seoul. The LG U+ Gasan data center is a state-of-the-art facility with a 75,000 m2 gross floor area and around 13,200 m2 datacentre room. Located in the Gasan Digital Complex, it benefits from a strategic location.
Varidata leverages Seoul’s robust network infrastructure and the support of the LG U+ data center to deliver fast, stable, and reliable connections between Seoul and China, as well as across the APAC region. By securely housing your data in the LG U+ data center, you can expand your global reach with confidence and ensure the safety of your valuable information.

Location Feature
| Wide Access LG U+ Gasan data center boasts ISP access to leading carriers such as Korea Telecom, LG U+, China Telecom, China Mobile, and others, enabling fast and secure connections within the APAC region. |
| Tier 3 Facility LG U+ Gasan data center adheres to the international Tier 3 standard, ensuring powerful and reliable performance through redundant components, enhanced security measures, and scalable infrastructure. |
| Location Advantages The LG U+ Gasan data center in Seoul, Seoul benefits from its strategic location in the Gasan Digital Complex, offering excellent connectivity, skilled talents, and a supportive business environment. |
| Great Capacity With the around 13,200 m2 data center room, it can accomodate 8,000 42U standard cabinets. |
| Brand Equity LG U+ is a leading internet data center operator in Seoul, known for its extensive experience and abundant resources. With their expertise, LG U+ offers customized solutions to meet the specific needs of businesses. |
| Reliable Power LG U+ Gasan data center is equipped with redundant UPS power, N+1 system with diesel generator, and dual storage battery system. These robust infrastructure components ensure uninterrupted and seamless operations. |
POWER SUPPLY
| Power Supply | Substation and high-capacity direct distribution method (dedicated line) | |||
| UPS | Dual redundancy of UPS power and physical circuit redundancy | |||
| Power Generator | N+1 system with diesel generator | |||
| Electricity Equipment | Dual storage battery system |


AIR CONDITIONING SYSTEM
| Cooling | Main supply cooling tower with backup emergency distributed cooling source and eight-zone distributed vertical piping configuration | |||
| Temperature | 22 -24 °C | |||
| Humidity | 30 -60% |
PROTECTION SYSTEM
| Seismic Design | A maximum ground acceleration of 0.2g applied (intensity level 7) | |||
| Flood Control Design | Location of safe zone with no nearby hazards Flood Safe Zone (2nd floor) location (7m from water level) |


DATA CENTER CONSTRUCTION AND SERVICE
| Building Design | 75,000 m2 gross floor area, and around 13,200 m2 datacentre room | |||
| Building Security System | Windowless exterior structure Installation of video surveillance system (state-of-the-art CCTV) | |||
| Service Support | 24-hour monitoring |
SECURITY SYSTEM
| Security Monitoring | 24/7 monitoring and operation of a centralized security room | |||
| Access Control | Data center access control. Card recognition access control |